Backnang, Germany

Project:Backnang, Germany
Partners:Digital Energy Solution, Germany
Performance:230.64 kWp
Mounting system:PMT Carport Double

A carport, which was realized with 744 modules and a total output of 230.64 kWp
. The carport was completely erected after 17 days.

The carport in detail:
Entry height: 2.65m
Angle of attack: 10°
Roof area: 1,306.62 m²
Cable routing: integrated

Our Monday team has done a very good job again. Many thanks for that.